Plans for Trumpington Campus – 2015

Key Dates:

December 2011  Appointment of Design Team finalised

April 2012  Contractor Selected

September 2012  Application for planning permission

April 2013  Completion of technical design.

*DESIGN REQUIREMENTS – key expectations

  • arrival, community presence and aesthetic value
  • circulation: corridors and hearts
  • community access: openness and safety
  • performance, display and collaboration
  • vertical integration
  • flexibility and adaptability
  • digital technology in learning and facilities management
  • environmental sustainability
  • transport*

Design team novated to contractor

May 2015  Construction complete

August 2015  SCHOOL OPENS